Artists rendering of the front.
![](images/house-front-color.JPG)
|
Picture of back of home built from the same plans somewhere in Canada.
![](images/house-back.JPG)
|
|
Main Floor
![](images/house-1.GIF)
|
Second floor.
![](images/house-2.GIF)
|
|
Some progress pictures...
- Perc Test April 5,2016
- More Perc Test
- Digging Infiltrator Trench April 13, 2016
- Start dig of foundation hole April 18, 2016
- foundation hole April 23, 2016
- septic tank hole April 23, 2016
- septic tank in place April 25, 2016
- footing forms May 7, 2016
- footings set and filled May 13, 2016
- building foundation wall forms May 22, 2016
- foundation walls May 27, 2016
- septic drain field passes county inspector June 8, 2016
- septic d-box to tank June 8, 2016
- utility line trench June 15, 2016
- begining to frame walls July 10, 2016
- glulam beams placed July 20, 2016
|
back
|
|